France says nuclear plant overruns 'unacceptable'
by Staff Writers
Paris (AFP) Sept 29, 2019

The French government on Sunday slammed as "unacceptable" delays and cost overruns at nuclear power plant projects undertaken by state utility firm EDF, including Britain's controversial Hinkley Point.

Finance and Economy Minister Bruno Le Maire said an independent audit would be launched and warned that France's nuclear industry could not be a "state within a state".

Electricite de France (EDF) had said last week that costs for Hinkley Point C were now estimated at 21.5-22.5 billion pounds ($26.8-28.1 billion), a rise of 1.9-2.9 billion pounds over previous estimates.

A similar EPR third generation nuclear power plant project in Olkiluoto in Finland is now 10 years behind the initial schedule, as is the Flamanville project in western France.

"The government issued warnings several months ago," Le Maire told LCI and RTL TV, saying the independent audit would be delivered on October 31.

"All this drifting is unacceptable. It is not up to the level of what EDF represents and the French expertise in the sector."

"I can understand that there could be a technical issue or a realisation problem. But when the delays accumulate you need to look at it independently and draw the conclusions," he said, warning of "consequences at all levels".

The novel European Pressurised Reactor (EPR) system aims to improve safety and efficiency. The French government owns a majority 83.7 percent stake in EDF.

EDF is part of a French-Chinese consortium awarded the two-reactor Hinkley Point project in 2016 despite criticism from green groups and cost warnings from experts.

It is supposed to provide seven percent of Britain's total power needs, according to the government. It is scheduled to start producing electricity in 2025 and has a projected operational lifetime of 60 years.


Related Links
Nuclear Power News - Nuclear Science, Nuclear Technology
Powering The World in the 21st Century at Energy-Daily.com


Thanks for being here;
We need your help. The SpaceDaily news network continues to grow but revenues have never been harder to maintain.

With the rise of Ad Blockers, and Facebook - our traditional revenue sources via quality network advertising continues to decline. And unlike so many other news sites, we don't have a paywall - with those annoying usernames and passwords.

Our news coverage takes time and effort to publish 365 days a year.

If you find our news sites informative and useful then please consider becoming a regular supporter or for now make a one off contribution.
SpaceDaily Contributor
$5 Billed Once


credit card or paypal
SpaceDaily Monthly Supporter
$5 Billed Monthly


paypal only


CIVIL NUCLEAR
More cost overruns, delays for UK nuclear project: EDF
Paris (AFP) Sept 25, 2019
Britain's controversial Hinkley Point nuclear power plant project faces substantial fresh cost overruns and further delay, France's EDF power giant said Wednesday. The company, part of a French-Chinese consortium awarded the two-reactor project in 2016 despite criticism from green groups and cost warnings from experts, warned that costs were "now estimated at between 21.5 and 22.5 billion pounds (24.4-25.5 billion euros/$26.8-28.1 billion)." That equates to a rise of between 1.9 and 2.9 billion ... read more

Comment using your Disqus, Facebook, Google or Twitter login.



Share this article via these popular social media networks
del.icio.usdel.icio.us DiggDigg RedditReddit GoogleGoogle

CIVIL NUCLEAR
CIVIL NUCLEAR
Marvellous Mars from the North Pole to the Southern Highlands

Drones probe dust devils to understand Mars's atmosphere

Deadline closing for names to fly on NASA's next Mars rover

3D models of Mars to aid ESA Rover in quest for ancient life

CIVIL NUCLEAR
Chinese researchers conduct in situ measurement of lunar dust at Chang'e-3 landing site

Lunar soil is a dangerous nuisance for astronauts

Orion to face simulated rigors of space in last major testing before Artemis I

Kentucky companies give NASA Artemis missions a boost

CIVIL NUCLEAR
Huge Volcano on Jupiter's Moon Io Erupts on Regular Schedule

Stony-iron meteoroid caused August impact flash at Jupiter

Storms on Jupiter are disturbing the planet's colorful belts

ALMA shows what's inside Jupiter's storms

CIVIL NUCLEAR
Researchers mix RNA and DNA to study how life's process began billions of years ago

Looking for alien lurkers

Research redefines lower limit for planet size habitability

First Water Detected on Planet in the Habitable Zone

CIVIL NUCLEAR
NASA joins last of five sections for Space Launch System rocket stage

Pad 39B water flow test comes through loud and clear

Baikonur Cosmodrome Getting Ready for Last Launch of Russian Rocket With Ukrainian Parts

Aerojet Rocketdyne Scores Big Contracts on US ICBM, Hypersonic Missile Programs

CIVIL NUCLEAR
China's KZ-1A rocket launches two satellites

China's newly launched communication satellite suffers abnormality

China launches first private rocket capable of carrying satellites

Chinese scientists say goodbye to Tiangong-2

CIVIL NUCLEAR
Comet's collapsing cliffs and bouncing boulders

Comet gateway discovered to inner solar system

Gigantic asteroid collision boosted biodiversity on Earth

NASA blames bad weather for failure to warn about approaching hazardous asteroid









The content herein, unless otherwise known to be public domain, are Copyright 1995-2024 - Space Media Network. All websites are published in Australia and are solely subject to Australian law and governed by Fair Use principals for news reporting and research purposes. AFP, UPI and IANS news wire stories are copyright Agence France-Presse, United Press International and Indo-Asia News Service. ESA news reports are copyright European Space Agency. All NASA sourced material is public domain. Additional copyrights may apply in whole or part to other bona fide parties. All articles labeled "by Staff Writers" include reports supplied to Space Media Network by industry news wires, PR agencies, corporate press officers and the like. Such articles are individually curated and edited by Space Media Network staff on the basis of the report's information value to our industry and professional readership. Advertising does not imply endorsement, agreement or approval of any opinions, statements or information provided by Space Media Network on any Web page published or hosted by Space Media Network. General Data Protection Regulation (GDPR) Statement Our advertisers use various cookies and the like to deliver the best ad banner available at one time. All network advertising suppliers have GDPR policies (Legitimate Interest) that conform with EU regulations for data collection. By using our websites you consent to cookie based advertising. If you do not agree with this then you must stop using the websites from May 25, 2018. Privacy Statement. Additional information can be found here at About Us.