Dismantling Germany's Lubmin nuclear plant, piece by piece
Dismantling Germany's Lubmin nuclear plant, piece by piece
By Sebastien ASH
Lubmin, Germany (AFP) April 11, 2023

At a former nuclear power plant near Lubmin on Germany's Baltic coast, workers in the disassembly hall are chopping up a bulky grey section of a pump from inside one of the reactors.

A bandsaw slowly eats its way through the part, cutting it into smaller chunks that will fit in the decontamination units.

Those pieces will be blasted with iron sand, removing a dangerous top layer of material to be packed up and stored away from harm.

In mid-April, Germany's last three nuclear plants will go offline. But as their working life comes to an end, the painstaking task of decommissioning and dismantling the units begins.

The facility near Lubmin, built by East Germany's communist government and also known as the Greifswald nuclear power plant, was closed in 1990 with reunification.

But it will still be several decades before the work here is done.

"These nuclear power plants were built to last forever," said Hartmut Schindel from site manager EWN, so taking the plant apart has been a learning process.

"No one was responsible for the decommissioning in the 1960s" when the plant was first designed, Schindel said.

- 'Massive amount' -

In all, workers at the plant have 1.8 million tonnes of material to sort through and shift.

"It's a massive amount," said Schindel, who first joined the plant in the former East Germany in 1976 and was later responsible for the disposal of nuclear waste.

The vast majority of the volume will be released for reuse after a lengthy administrative process, but a small percentage of contaminated material must be sequestered.

Access to the disassembly area is closely controlled. Workers strip off their clothes, put on standard-issue underwear and a bright orange jumpsuit before they can enter the hall.

Exposure to radiation inside is counted by a personal meter carried in a breast pocket.

Coming out, a cubicle that speaks with a woman's voice checks for contamination, counting down from 20, asking the individual to turn around and starting the timer again before opening the exit.

Among the last items to be disposed are large components from the centre of the reactors, stored in a vast hangar on site.

Six pressure vessels and 21 steam generators lacquered in bright colours are waiting here to be chopped up.

For these, EWN is erecting a completely new disassembly hall, set to be completed in 2025.

The unit, where the most radioactive parts from the core will be sawed up under water for safety reasons, is an experimental project that could serve as a model for other decommissioning efforts, said EWN spokesman Kurt Radloff.

Meanwhile the work at the plant is set to continue into the 2060s, a good 70 years after it closed, with a total cost in the "high single-digit" billions of euros, Radloff said.

- 'More complex' -

The process of dismantling the communist nuclear plants was "more complex", not least because information was "lost" during reunification, said Christian von Hirschhausen of the think tank DIW.

But even dismantling some of the western plants could still take 30 or 40 years, von Hirschhausen said.

What is more, it was already "foreseeable" that some 23 billion euros ($25 billion) set aside for decommissioning would not be enough, he said.

"The question is then, who will pay for the additional costs?"

In all, Germany will have 29 closed reactors to decommission once the final three plants go offline.

The country's last nuclear power plants were kept running longer than planned amid fears of an energy crisis sparked by Russia's curtailing of gas exports during the Ukraine war.

But the end of nuclear is a settled debate in Germany, where atomic energy has long been a sensitive issue.

While other countries are planning new projects, the idea of a nuclear revival in Germany does not appeal to Schindel, who will retire before the works at the plant are done.

"The future does not point towards nuclear energy but other forms of energy," he said.

How to decommission a nuclear power plant
Frankfurt, Germany (AFP) April 11, 2023 - Germany's last three nuclear power plants will stop generating electricity from Saturday, but the arduous and decades-long process of decommissioning the sites is only just beginning.

Here's a look at what happens after the plants are taken offline.

- Gradual shutdown -

On the day of the shutdown, plant operators will gradually decrease electricity output.

From 10:00 pm (2000 GMT), "we will lower the facility's power output by 10 megawatts per minute," Carsten Mueller, plant manager for the Isar 2 site near Munich, told the Bild newspaper.

When the reactor's power level drops to around 30 percent, "no more electricity will be fed into the high-voltage network and the generator will be automatically disconnected from the power grid", he said.

A similar process will take place in the turbines of the Emsland plant in Germany's northwest, and at Neckarwestheim in the southwest.

The Neckarwestheim plant has already been running "at about 70 percent capacity" since mid-January, said Joerg Michels, head of the nuclear power division at energy company EnBW, which operates the site.

Bringing a nuclear plant to a halt is actually a "routine process" often used during inspections, Michels said.

"What's unusual now is that it will happen for the last time."

Once the nuclear reactor is rendered less powerful it will no longer send hot, pressurised water to the machine room, where the turbines will subsequently stop producing electricity.

Although no ceremonies are planned at Neckarwestheim to mark the occasion, management will be on-site "out of respect" for the roughly 650 remaining employees, Michels said.

- Cooling and dismantling -

Over the following days, the atomic chain reaction sustained by the nuclear fuel rods will be "completely stopped" to allow for the "cooling of the plant's nuclear cycle," Michels said.

As part of its exit from atomic energy, Germany has opted for the immediate dismantling of the plants once they have been disconnected from the grid, rather than mothballing the facilities.

At Neckarwestheim, the 193 fuel elements in the reactor's core -- which are still highly radioactive -- will be transferred to a water-filled pool in an adjacent building.

The fuel elements will remain immersed for three to five years until they are packed into special "Castor" casks for interim storage.

The dismantling of each component of the power plant will start "at the beginning of next year," once all the permits have been obtained, Michels said.

"We are well prepared," he added, given that EnBW already has four other reactors undergoing dismantling.

The dismantling of Germany's last three nuclear installations is expected to take around 15 years.

- Final resting place -

Germany plans to bury its highly radioactive waste deep in the ground.

But the decision on where exactly this last resting place should be is taking longer than planned -- with suggested locations often running into opposition from nearby residents who fear health hazards.

A choice on the final repository was initially due by 2031, with the aim of having the site be operational by 2050.

But late last year the German body in charge of nuclear waste disposal said a suitable location would likely be found only between 2046 and 2068.

Once the site has been identified, the planning, licensing and construction of the repository is expected to take around two decades.

The final repository eventually selected must be able to safely store radioactive waste for a million years.

In the meantime, the highly radioactive waste will be held in specially designed interim storage facilities.

For medium- and low-level radioactive waste, a permanent repository has already been found at the former Konrad iron ore mine near Salzgitter in central Germany. The site is set to become operational in 2027.

"More than 30,000 generations will still be affected by the consequences of nuclear power technology, which has only been used in our country for 60 years," former environment minister Barbara Hendricks said in 2017.

Related Links
Nuclear Power News - Nuclear Science, Nuclear Technology
Powering The World in the 21st Century at Energy-Daily.com

Subscribe Free To Our Daily Newsletters
Tweet

RELATED CONTENT
The following news reports may link to other Space Media Network websites.
CIVIL NUCLEAR
The ups and downs of the global nuclear industry
Paris (AFP) April 11, 2023
As Germany prepares to shut its last nuclear reactors for good, other countries are turning to nuclear as a means of boosting their energy independence and cutting fossil fuel emissions. Here is a global snapshot of the controversial industry, which has seen some improvement in its fortunes but whose long-term future remains uncertain. - Post-Fukushima setback - Nuclear power is currently used in 31 countries - Germany excluded - and accounts for around 10 percent of electricity generated ... read more

CIVIL NUCLEAR
CIVIL NUCLEAR
Ready for Software Upgrade Sols 3786-3788

MOXIE Celebrates 2 Years on Mars: Discoveries and Work Left To Do

First Mars Sample Depot shaped by Rover, Lander, and Helicopter

NASA's Perseverance Collects First Mars Sample of New Science Campaign

CIVIL NUCLEAR
NASA's first flight with crew critical to long-term return to the moon

First woman, Black astronaut, Canadian to make 2024 flight around Moon

NASA to reveal crew for 2024 flight around the Moon

U.S. Navy pilot to become first person of color to go to the moon

CIVIL NUCLEAR
Sabotaging Juice

Redness of Neptunian asteroids sheds light on early Solar System

Hubble monitors changing weather and seasons at Jupiter and Uranus

An explaination for unusual radar signatures in the outer solar system

CIVIL NUCLEAR
Do Earth-like exoplanets have magnetic fields

New paper investigates exoplanet climates

JWST confirms giant planet atmospheres vary widely

Planet hunting and the origins of life

CIVIL NUCLEAR
Musk's Twitter marks BBC, NPR as 'government funded' but not Tesla or SpaceX

Privately built, liquid-fuel rocket first in world to reach orbit in debut flight

Virgin Orbit files for bankruptcy, seeks buyer

Momentus' pioneering propulsion system completes initial tests in space

CIVIL NUCLEAR
China's inland space launch site advances commercial services

China's Shenzhou XV astronauts complete 3rd spacewalk

China's Shenzhou-15 astronauts to return in June

China's space technology institute sees launches of 400 spacecraft

CIVIL NUCLEAR
Psyche updated plan puts mission on track for October launch

Two meteorites are providing a detailed look into outer space

NASA prepares for historic asteroid sample delivery on Sept 24

Large asteroid to zoom between Earth and Moon

Subscribe Free To Our Daily Newsletters




The content herein, unless otherwise known to be public domain, are Copyright 1995-2024 - Space Media Network. All websites are published in Australia and are solely subject to Australian law and governed by Fair Use principals for news reporting and research purposes. AFP, UPI and IANS news wire stories are copyright Agence France-Presse, United Press International and Indo-Asia News Service. ESA news reports are copyright European Space Agency. All NASA sourced material is public domain. Additional copyrights may apply in whole or part to other bona fide parties. All articles labeled "by Staff Writers" include reports supplied to Space Media Network by industry news wires, PR agencies, corporate press officers and the like. Such articles are individually curated and edited by Space Media Network staff on the basis of the report's information value to our industry and professional readership. Advertising does not imply endorsement, agreement or approval of any opinions, statements or information provided by Space Media Network on any Web page published or hosted by Space Media Network. General Data Protection Regulation (GDPR) Statement Our advertisers use various cookies and the like to deliver the best ad banner available at one time. All network advertising suppliers have GDPR policies (Legitimate Interest) that conform with EU regulations for data collection. By using our websites you consent to cookie based advertising. If you do not agree with this then you must stop using the websites from May 25, 2018. Privacy Statement. Additional information can be found here at About Us.