Successful Design Review: ATV Gets Go-Ahead

The International Space Station (ISS) depends on regular deliveries of experimental equipment and spare parts as well as food, air and water for its permanent crew. From Autumn 2004 onward, Europe's Automated Transfer Vehicle (ATV) will be one of the indispensable ISS supply spaceships.

Paris (ESA) Jun 25, 2003
In early June 2003, the Automated Transfer Vehicle (ATV) programme reached a milestone in successfully passing the Critical Design Review (CDR) during which some 140 international space experts expressed their full confidence in the design of the vehicle after analysing 55,000 pages of technical documentation.

Over the past three and a half months, around 40 engineers from the RSC Energia, 25 from NASA and over 50 from ESA, CNES and Arianespace conducted a full review of the ATV programme through its extensive documentation (presented in electronic format) and did not find anything wrong which would require a change in the design.

Seven panels, each consisting of 15 to 20 people, were charged with thoroughly reviewing the various aspects of the programme, such as avionics, systems, software, structure, thermics, as well as quality and operations. Teams from ESA and prime contractor EADS-LV answered their questions and clarification requests.

"The successful completion of the Critical Design Review for the ATV is an extremely important milestone for Europe's contribution to the ISS. The way is now free for the assembly of the first ATV, Jules Verne, and its maiden flight planned for September 2004. Together with the Columbus laboratory, ATV is a key European element," said J¿rg Feustel-B¿echl, ESA's Director of Human Spaceflight.

The purpose of the review was to assess and certify that the ATV design and operations concept meets the requirements for performance, reliability, and safety. The ATV project manager, Robert Lain¿, compared the CDR process to sieving through the complete programme to find possible bugs.

"The members of these external panels raised some good questions," said Lain¿. "Such as asking how the ATV could depart if the ISS was in a critical attitude, or if the ATV should have an extra software backup for re-entry. These remarks are very beneficial, because they help us to think about solutions to possible problems before flying".

In 2000, the Preliminary Design Review (PDR) had to be extended by six months to rethink the overall concept of navigation and guidance, rewrite some specifications and make a few hardware changes.

For example, another set of optical sensors (Videometre) was added for rendezvous and docking, and a set of Variable Conductance Heat Pipes (VCHP) was added to cope with large changes in power dissipation in the avionics bay of the spacecraft during orbit.

The successful conclusion of the review is important for the ATV programme since 90% of the flight hardware is already built and the final assembly process started. Any design change would have significantly impacted the scheduled launch of Jules Verne set for September 2004.

"The programme is ready to proceed to the next step, yet there is significant work to be done to complete ATV. But we didn't see any design issues that would be a cause to stop or pause. The ATV is on a tight schedule with many challenges ahead.

"It's scheduled to fly in September 2004, but the team is well prepared and the design is ready to go into final build", said Bill Gerstenmaier, the International Space Station Programme Manager at NASA who came to ESA's European Space and Technology Centre (ESTEC) in Noordwijk, The Netherlands, June 4 to attend the final CDR board meeting.

"The success of CDR was a joint effort of European industry and the ESA management team with important involvement of our Russian partners Rosaviakosmos and RSC Energia and full support from the NASA programme team. All contributors should be congratulated for their commitment and encouraged to complete the development of this highly complex spacecraft," said Feustel-B¿echl.

Related Links
ATV Program
SpaceDaily
Search SpaceDaily
Subscribe To SpaceDaily Express

Draper Lab Brings A New Age Of Automation To ISS
Boston - Jun 22, 2003
Early in the morning June 10, NASA ushered in a new era in International Space Station payload operations when payload controllers at the Marshall Space Flight Center (MSFC) installed the first Timeliner automation scripts.

   Add to Delicious





Memory Foam Mattress Review

Newsletters :: SpaceDaily Express :: SpaceWar Express :: TerraDaily Express :: Energy Daily
XML Feeds :: Space News :: Earth News :: War News :: Solar Energy News
  • Alcatel Space and Astrium forge agreement for AlphaBus
  • Europe's First Master Control Centre For Satellite Navigation
  • Alcatel Wins Pan African Telco Satellite
  • Alcatel Wins $160 Million Contract For Koreasat 5

  • Chemical Turns Stem Cells Into Neurons
  • Distant Doctors Make Their Rounds Via Satellite
  • Satellite's Role In Telemedicine
  • What Happens to the Brain in Space?

  • T-Rays Uncover Defects in Space Shuttle Foam Sample
  • Acoustics Research Provides Insight To Cause Of Shuttle Loss
  • NASA May Offer Scientific Community Opportunity To Study Columbia Debris
  • Columbia Accident Investigation Board Releases Working Scenario

  • Successful Design Review: ATV Gets Go-Ahead
  • European Experiment Hardware Reaches ISS
  • Draper Lab Brings A New Age Of Automation To ISS
  • First Soybeans Grown in Space Similar to Earth-Grown Crops

  • Wright Flyer Takes To The Sky In Las Vegas
  • Aurora Builds Low-speed Wind Tunnel
  • Yeager To Retire From Military Flying After October Airshow
  • Yeager To Retire From Military Flying After October Airshow

  • Foam Strip Hitting Shuttle Most Likely Cause Of Accident
  • Japan's MV Returns To Service With Muses-C Launch
  • Utah State's SDL Launches Rocket To Study Bowshock Heating
  • SpaceX Beefs Up Marketing With DC Office

  • First Mars, Then Venus With Starsem Express
  • Rockot Multiple Orbit Mission Hits Different Orbits
  • Sea Launch Lofts Thuraya-2 Mobile Comms Bird
  • Atlas V Team Begins Launch Preparations for AV-003

  • Fire Scout UAV Performs Lost Comms Autonomous Recovery And Shutdown
  • US And Germany Step Up Plans For Global Hawk Elint Demonstration
  • Watchkeeper UAV Equipped With Tactical Synthetic Aperture Radar
  • Hunter UAV Gets Tactical With New Radar Systems

  • The content herein, unless otherwise known to be public domain, are Copyright 1995-2006 - SpaceDaily.AFP and UPI Wire Stories are copyright Agence France-Presse and United Press International. ESA PortalReports are copyright European Space Agency. All NASA sourced material is public domain. Additionalcopyrights may apply in whole or part to other bona fide parties. Advertising does not imply endorsement,agreement or approval of any opinions, statements or information provided by SpaceDaily on any Web page published or hosted by SpaceDaily. Privacy Statement