Gordon, Udall Urge NASA to Heed GAO's Project Management Recommendations

Credits: Pat Rawlings.
by Staff Writers
Washington DC (SPX) Jan 24, 2006
After careful study, the National Aeronautics and Space Agency's (NASA) policies governing the development of space flight systems have been found to be lacking some key criteria. A report released today by the Government Accountability Office (GAO) concluded that additional "decision reviews" are needed to ensure that NASA's projects meet their performance, cost, and schedule goals.

The GAO study, requested in June 2005 by House Science Committee Ranking Member Bart Gordon (D-TN) and Space and Aeronautics Subcommittee Ranking Member Mark Udall (D-CO), is part of Science Democrats' ongoing oversight agenda for NASA.

"As NASA embarks on an initiative to return American astronauts to the Moon - an endeavor estimated to cost more than $100 billion over the next 13 years - we need to have confidence that the agency will be good stewards of taxpayer dollars," stated Rep. Gordon. "In its report out today, the GAO offers some common-sense recommendations aimed at reducing the chances that NASA's projects will suffer cost growth and schedule delays. I hope NASA will take the GAO's guidance seriously."

GAO's recommendations include requiring that NASA projects demonstrate:

  • that key technologies have reached a high maturity level before approving the projects for transition from the formulation to the implementation phase,
  • that the design is stable before approving the projects for transition from the design phase to the fabrication, assembly, and test phase; and
  • that the design can be manufactured within cost and schedule and meet quality targets prior to any decision to enter into production.

    In addition, the GAO recommends that NASA include additional decision reviews that are tied to the key phases of a project "to increase the likelihood that cost, schedule, and performance requirements of the project will be met."

    "The GAO report cautions that 'several of NASA's major acquisitions have been marked by cost, schedule, and performance problems,'" added Rep. Udall. "'Yet, the challenges NASA faces in the future are likely to far exceed those it has faced in the past.' I want NASA to succeed on all of its important missions in science, aeronautics, and human space flight."

    "Good project management is going to be critical to NASA's mission success, and I welcome GAO's constructive recommendations to the agency. Over the coming year, we plan to follow NASA's progress in implementing them," concluded Rep. Gordon.

    The GAO report is entitled "NASA: Implementing a Knowledge-Based Acquisition Framework Could Lead to Better Investment Decisions and Project Outcomes." [GAO-06-218].

    Related Links
    GAO 06-218 Report

    Gov't Plan To Send First South Korean Into Space Likely To Be Delayed
    Seoul, South Korea (SPX) Jan 24, 2006
    South Korea's plan to send its first astronaut into space within the first half of 2007 is likely to be delayed following a rescheduling request by Russia, the Science Ministry said Friday, reports Asia Pulse.

       Add to Delicious





  • Memory Foam Mattress Review

    Newsletters :: SpaceDaily Express :: SpaceWar Express :: TerraDaily Express :: Energy Daily
    XML Feeds :: Space News :: Earth News :: War News :: Solar Energy News
  • EchoStar Places $1.5 Billion In Senior Notes
  • ChinaSat 6B To Beam More TV Channels
  • Sciemus And Liberty Syndicates Revolutionise Sat Insurance
  • Skyworks Ramps Innovative CMOS Switches Into Volume Production With Several Customers

  • Florida Tech, FSRI Receive $1.3 Million Federal Grant For Space Research
  • Researchers Make Long DNA Wires For Future Medical And Electronic Devices
  • One Small Step Means Giant Leap For Spinal Cord Research
  • Tiny Self-Assembling Cubes Could Carry Medicine, Cell Therapy

  • NASA Awards Shuttle/Space Station Engineering Support Contract
  • Happy Anniversary Shuttle Crawlers
  • NASA's Soyuz Deal Will Not Scrap Shuttle
  • Griffin Vows To Send Shuttle Mission To Hubble

  • Next Space Station Delivery Postponed
  • Expedition 12 Prepare For Their Second Spacewalk
  • Spacehab Enters Race For Commercial Space Station Supply Work
  • NASA Seeks Proposals For Crew And Cargo Transportation To Orbit

  • Boeing Awarded Canadian CF-18 Avionics Upgrade
  • US Air Force Rates F-22A Raptor "Mission Capable"
  • Wedgetail Aircraft Delivered To Boeing Australia
  • Northrop Grumman To Provide New Air Data Inertial Reference Units To Lufthansa

  • XCOR Completes Methane Engine Pulse Fire Tests
  • ISRO To Launch Indigenous Cryogenic Engine This Year
  • Falcon 1 To Launch February 8
  • Successful First Test For Vega's Zefiro 9 Engine

  • Eutelsat's Hot Bird 7A Arrives At Kourou From Alcatel Alenia Space Facilities
  • Russian Proton-M To Launch Arab Satellite From Baikonur March 1
  • Sea Launch Begins A Sold-Out Year
  • H-2A To Launch Today

  • USAF Take Delivery Of First Production Global Hawks
  • Northrop Grumman's Navy Fire Scout Gets Its Sea Legs
  • NG Takes Delivery Of MQ-8B Fire Scout UAV Airframe
  • Geneva Completes First Stage Of US Navy Project

  • The content herein, unless otherwise known to be public domain, are Copyright 1995-2006 - SpaceDaily.AFP and UPI Wire Stories are copyright Agence France-Presse and United Press International. ESA PortalReports are copyright European Space Agency. All NASA sourced material is public domain. Additionalcopyrights may apply in whole or part to other bona fide parties. Advertising does not imply endorsement,agreement or approval of any opinions, statements or information provided by SpaceDaily on any Web page published or hosted by SpaceDaily. Privacy Statement